Offloading wind mill components 2014

E. Helaakoski Oy offloaded a ship full of wind mill components heading for a nearby wind park. Nacelles and blades were offloaded onto dry land in good summer weather.

Six nacelles, each weighing around 140 tons were lifted with only one crane, LIEBHERR LTM 1500-8.1. The 500 ton capacity crane performed the task perfectly.

60-meter blades were lifted in tandem (Terex AC 250 and Liebherr LTM 1200-5.1). Also, several 30-ton hubs were offloaded consecutively.

With proactive planning and careful execution, all lifts were carried out without interruptions.